# PL2026 Timeline & Milestones

## PL2026 Timeline

The following Gantt chart illustrates the complete PL2026 development timeline, including management activities, development phases, ALMA testing cycles, and delivery milestones.

```mermaid
gantt
    title PL2026 Timeline
    dateFormat  YYYY-MM-DD
    tickInterval 1month
    excludes weekends

    section Management
    %% Stakeholder Planning & Prioritization       :active, des1, 2025-10-01, 2025-12-31
    %% Team F2F Meeting, Charlottesville, VA       :active,       2025-10-13, 5d
    Inform ALMA AQUA/Archive of New Products    :active, milestone, 2026-05-01, 1d

    section Development
    New Features, Bugfixes, Refactoring, Testing, Documentation :active,       2026-02-01, 2026-07-01
    %% VLASS Feature Dev Complete            :active, milestone, 2026-02-01, 1d
    VLASS Branch release/2026.1.0         :active, milestone, 2026-03-06, 1d
    CASA Branch PL2026                    :active, milestone, 2026-02-15, 1d
    %% ALMA/VLA Feature Dev Complete         :active, milestone, 2026-07-01, 1d
    ALMA/VLA Branch release/2026.2.0      :active, milestone, 2026-07-01, 1d
    Optimization & Bugfixes               :active, 2026-07-01, 2026-07-31

    section ALMA Testing
    %% Ref. Benchmark (late-PL2025)         :active, 2025-10-01, 2025-11-15
    Ref. Benchmark (early-PL2026)        :active, 2026-02-15, 2026-03-31
    Validation Benchmark (PL2026)        :active, 2026-06-15, 2026-07-31
    TRR1 (pre-E2E) Observations          :milestone, 2026-05-14, 1d
    TRR1                                 :test1, 2026-05-14, 2026-05-22
    TRR1 Report on Data Reduction        :milestone, 2026-05-22, 1d
    TRR2 (24h) Observations              :milestone, 2026-07-09, 1d
    TRR2                                 :test2, 2026-07-09, 2026-07-23
    TRR2 Report on Data Reduction        :milestone, 2026-07-23, 1d
    Acceptance (48h) Observations        :milestone, 2026-08-18, 2d
    Acceptance                           :test3, 2026-08-18, 2026-09-02
    Acceptance Report on Data Reduction  :milestone, 2026-09-03, 1d
    JAO-ARC Validation Test              :test4, 2026-09-03, 2026-09-14

    section Delivery
    %% ALMA Cycle-12 and VLA/SRDP Pipeline (2025.1.0.35, CASA 6.6.6-17-py3.10)  :done, crit, milestone, 2025-10-01, 1d  
    ALMA Cycle-12 and VLA/SRDP Pipeline patch-1 (2025.1.0.36, CASA 6.6.6-18-py3.10)  :done, crit, milestone, 2026-03-01, 1d      
    VLASS Pipeline (2026.1.0.4, CASA 6.7.1-13-py3.10+gpu)             :active, crit, milestone, 2026-04-20, 1d
    ALMA E2E13 Pre-release                :active, crit, milestone, 2026-07-10, 1d
    ALMA Cycle-13 and VLA/SRDP Pipeline (2026.2.0, CASA 6.7.4-py3.12)     :active, crit, milestone, 2026-08-01, 1d
```

---

## Key Milestones

### Delivery Schedule

March 2026 (patch release)
: **ALMA Cycle-12 and VLA/SRDP Pipeline patch-1**

  - Version: 2025.1.0.37
  - CASA: 6.6.6-18-py3.10
  - Status: Completed

April 2026
: **VLASS Pipeline**

  - Version: 2026.1.0.4
  - CASA: 6.7.1-13-py3.10+gpu
  - Status: Completed

July 2026
: **ALMA E2E13 Pre-release**

  - Version: 2026.2.0 (pre-release)
  - Status: Planned

August 2026
: **ALMA Cycle-13 and VLA/SRDP Pipeline**

  - Version: 2026.2.0
  - CASA: 6.7.4-py3.12
  - Status: Planned

### ALMA Testing Schedule

May 14, 2026
: **TRR1 (pre-E2E) Observations**

May 22, 2026
: **TRR1 Report on Data Reduction**

July 9, 2026
: **TRR2 (24h) Observations**

July 23, 2026
: **TRR2 Report on Data Reduction**

Aug 18–19, 2026
: **Acceptance (48h) Observations**

Sep 3, 2026
: **Acceptance Report on Data Reduction**

---

## PL2025/2026 Branching Strategy

The branching diagram below illustrates the development workflow across PL2025 and PL2026 cycles, showing the relationship between the main development branch and release branches.

### Branch Overview

- **Main Branch**: Continuous development with new features and improvements
- **release/2025.1.0**: Stable release for ALMA Cycle-12 (CASA 6.6.6-py3.10)
- **release/2026.1.0**: VLASS-focused release (CASA 6.7.1-py3.10-gpu)
- **release/2026.2.0**: ALMA Cycle-13 and VLA release (CASA 6.7.x-py3.12)

### Development Phases

1. **Feature Development**

   - New features developed on main branch
   - Feature branches merged back to main
   - Regular integration and testing

2. **Release Branching**

   - Release branches created at feature freeze
   - Stabilization and bug fixes on release branches
   - Critical fixes cherry-picked back to main

3. **Maintenance**

   - Hotfixes applied to release branches
   - Important fixes backported as needed
   - Main branch continues with new development

```mermaid
%%{init: {'logLevel': 'debug', 'theme': 'base', 'gitGraph': {'showBranches': true, 'showCommitLabel': true, 'mainBranchOrder': 1}}}%%
gitGraph
    %% === Initial 2025 Development on Main ===
    commit id:"feature1"
    commit id:"feature2"
    commit id:"feature3"
    commit id:"bugfix1" tag:"2025.0.2.14" tag:"2025.1.0.0" tag:"2025.1.1.0"

    %% --- Branch for 2025.1.0 Release ---
    branch "release/2025.1.0 (casa-6.6.6-py3.10)" order: 0
    checkout "release/2025.1.0 (casa-6.6.6-py3.10)"
    commit id:"bugfix2"
    commit id:"bugfix3" tag:"2025.1.0.35" type: HIGHLIGHT
    checkout main

    %% === Continued Development on Main ===
    commit id:"refactor1"
    commit id:"refactor2"
    branch "feature4" order: 2
    checkout "feature4"
    commit id:"feature4-pt1"
    commit id:"feature4-pt2"
    checkout main
    cherry-pick id:"bugfix2" tag:"2025.1.1.x"
    cherry-pick id:"bugfix3" tag:"2025.1.1.27"
    merge "feature4" id:"merge:feature4"
    commit id:"feature4"
    commit id:"bugfix4" tag:"2025.1.1.10"
    commit id:"feature5"
    commit id:"feature6" tag:"2026.0.0.0"

    %% === VLASS 2026 Development ===
    commit id:"feature7"
    commit id:"bugfix5" tag:"2026.0.1.0"
    commit id:"bugfix6"
    commit id:"feature8" tag:"2026.0.1.14" tag:"2026.1.0.0" tag:"2026.1.1.0"

    %% --- Branch for 2026.1.0 (VLASS) Release ---
    branch "release/2026.1.0 (casa-6.7.1-py3.10-gpu)" order: 3
    checkout "release/2026.1.0 (casa-6.7.1-py3.10-gpu)"
    commit id:"bugfix7"
    commit id:"bugfix8" tag:"2026.1.0.2"
    commit id:"hotfix1"
    commit id:"hotfix2" tag:"2026.1.0.3" type: HIGHLIGHT
    checkout main

    %% === ALMA/VLA 2026 Development ===
    commit id:"feature9" tag:"2026.1.1.1"
    cherry-pick id:"bugfix7" tag:"2026.1.1.2"
    commit id:"feature10"
    commit id:"feature11" tag:"2026.1.2.0"
    commit id:"feature12"
    commit id:"bugfix9" tag:"2026.1.3.7" tag:"2026.2.0.0" tag:"2026.3.0.0"

    %% --- Branch for 2026.2.0 (ALMA/VLA) Release ---
    branch "release/2026.2.0 (casa-6.7.x-py3.12)" order: 4
    checkout "release/2026.2.0 (casa-6.7.x-py3.12)"
    commit id:"bugfix10"
    commit id:"hotfix3" tag:"2026.2.0.5"
    checkout main

    %% === Post-Release Maintenance & Mainline Dev ===
    commit id:"refactor3" tag:"2026.3.0.1"
    commit id:"bugfix11" tag:"2026.2.0.2"
    cherry-pick id:"hotfix3" tag:"2026.3.0.7"
    commit id:"refactor4"
    commit id:"refactor5"
    checkout "release/2026.2.0 (casa-6.7.x-py3.12)"
    cherry-pick id:"bugfix11" tag:"2026.2.0.3"
    commit id:"hotfix4" tag:"2026.2.0.4" type: HIGHLIGHT
```

---

For version string format, see {doc}`devel/reference/versioning`.